Main Runway resurfacing

Main Runway Resurfacing Complete 

Essential resurfacing of BNE’s main runway was recently completed after six months of night works involving up to 100 personnel and 60 items of plant and equipment per shift. More than 200,000 work hours and 18,000 tonnes of asphalt have been employed in this project, at an investment of around $15 million.The resurfacing, which was conducted between midnight and 5am up to six nights a week, replaced the existing 11 year old asphalt in the touchdown zones at either end of the runway with asphalt produced onsite at a specially constructed mobile batch plant.

 

The new asphalt will provide a high quality runway surface for at least the next 10 years.This project was successfully completed in September without any unplanned delays. 

 

Fact sheet on the works here

 

Footage of the works

 

 

Below: A map demonstrating the works areas and staging. Open here for a larger view

 

If you have any queries regarding this work program, please contact Alex Heather via email: BACoverlayworks@bne.com.au

Brisbane Airport background