iOS app Android app View apps View mobile website

Terminal - Service Upgrades

INTERNATIONAL TERMINAL SELF-SERVICE CHECK-IN AND AUTOMATIC BAG DROP

   

>Timing: January 2015 to April 2018

> Investment: $12.6 million

> Construction jobs: 110

 

Brisbane Airport Corporation (BAC) is continuing to deliver world first technology with new self-service check-in and automatic bag drop (ABD) facilities at the International Terminal.

 

When complete, the $2.6m project will deliver 96 new self-service kiosks and 32 new automatic bag drops to rows 2, 3, 8 and 9 on Level Four of the terminal, resulting in quicker check-in for passengers and shorter queues.

 

The new self-service check-in kiosks were all installed by December 2016, with the final stage of the project, the automatic bag drops scheduled to run from January 2017 to April 2018.

 

Project Timing:

January to late March 2017: Installation of eight ABD units to check-in Row 8

Mid April to late June 2017: Installation of eight ABD units to check-in Row 2

Late September to late November 2017: Installation of eight ABD units to check-in Row 3

Early February 2018 to April 2018: Installation of eight ABD units to check-in Row 9

 

INTERNATIONAL TERMINAL EMERGENCY LIGHTING UPGRADE

 

> Timing: Early October 2017 to April 2018

> Investment: $1.7 million

 

While the current ITB emergency lighting system is fully compliant with all Australian safety standards, the continuing growth in passenger numbers and subsequent expansion of the terminal requires an upgrade of services.

 

When complete the project will provide the following benefits:

* A new modern, remotely monitored and fully functional single unit emergency lighting system.

* Improved overall system performance.

 

The project will be carried out in stages to ensure minimum disruption to Terminal operations.

High level staging plans as of September 2017 are:

Stage 1: Early October to late November – initial exploratory work to assist in the development of detailed staging plans; location and logging of all existing emergency lighting.

Stage 2: Late October to early 2018 – replacement of all emergency lighting and exit signage in public areas throughout terminal.

Stage 3: Late October to April 2018 – replacement of all emergency lighting and exit signage in retail tenancies and offices.

 

DOMESTIC TERMINAL FIRE SERVICES UPGRADE

 

   

> Timing: November 2016 to October 2017

> Investment: $29 million

> Construction jobs: 45

 

While the current DTB Fire System is fully compliant with all Australian safety standards, increasing passenger numbers and the continuing expansion of the Terminal requires an upgrade of services. The works will provide upgrades of the existing smoke detection system, existing emergency lighting and exit signs, existing sound and intercom system, new ‘dry’ system fire alarm services and improved overall system performance.

 

More information

 

INTERNATIONAL TERMINAL ENTRY CONTROL POINT UPGRADE

 

   

> Timing: Completed

> Investment: $2.4 million

 

Brisbane Airport Corporation (BAC) and the Department of Immigration and Border Protection (DIBP) have upgraded the Entry Control Point (ECP) facilities at Level Two Arrivals in the International Terminal.

 

The project has further improved passenger flow through the arrivals area thanks to a redesigned arrivals process, improved way finding signage, clearly marked passenger channels, relocation and expansion of concourse automated Smart Gate kiosks, improved lighting and new floor finishes.

 

More information 

 

INTERNATIONAL TERMINAL SMART GATES EXPANSION

 

>Timing: Completed

> Investment: $6 million

 

Brisbane Airport Corporation (BAC) and the Department of Immigration and Border Protection (DIBP) have expanded the automated Border Control Smart Gate facilities at the International Terminal.  The project delivered 12 new Smart Gate kiosks on the Departures level and a further 11 gates at Arrivals.  The automated border controls have resulted in faster processing of passengers and reduced queue times in Passport Control. 

More information 

 

INTERNATIONAL TERMINAL BATHROOM UPGRADE

 

   

> Timing: Completed

> Investment: $1.1 million

 

Brisbane Airport Corporation (BAC) has upgraded bathrooms at the northern end of the ITB on Level 3 Departures.

The project delivered re-furbished male and female bathrooms, re-furbished Parents Room, a newly tiled bathroom corridor, re-furbished northern concourse bathroom and Smokers Area

 

More information

 

TERMINAL ESCALATORS UPGRADES

 

   

 

>Timing: Completed

> Investment: $1.5 million

 

Brisbane Airport Corporation (BAC) has completed upgrading escalators at the International and Domestic terminals. While the previous escalator system was fully compliant with all Australian safety standards, increasing passenger numbers and the continuing expansion of both terminals required an upgrade of services. The works delivered new glass panel fall protection to improve safety and security, new under-step lighting to assist users and more external lighting along the escalators.

 

More information

 

 

DOMESTIC TERMINAL ROOF REFURBISHMENT

  

>Timing: Complete

>Investment: $3 million

 

High winds, unprecedented rainfall and extreme temperatures topping 50 degrees were just some of the challenges overcome by the team working on Brisbane Airport’s Domestic Terminal roof refurbishment.The $3m, yearlong project is now complete, with the entire roof cleaned, repaired and re-coated, prolonging its life for the next 25 years.

 

More information

Watch Video

 

 

 

 

Brisbane Airport background